B.C. chiefs are demanding a national Indigenous consultation standard after saying the government sprinted past them on a big oil pipeline decision. At a gathering in Vancouver this week, chiefs told federal officials they were handed just eleven working days to review and respond to the decision that made the Pacific Link pipeline a project of national interest, according to The Canadian Press.
What the Pacific Link pipeline actually is
On October first, Prime Minister Mark Carney stood next to Alberta Premier Danielle Smith in Fort McMurray and fast-tracked a proposed oil line that could carry one million barrels a day to the Pacific coast. According to the Associated Press, the route would run about twelve hundred and fifty kilometres from Bruderheim, Alberta, to a deep water port near Delta, B.C., mostly following the existing Trans Mountain corridor.
The pitch is about leverage. Carney said that today ninety percent of Alberta's oil goes to the United States, and that the project would "materially reduce that dependence" by opening doors to Asian buyers. It also lands at a delicate political moment, because Alberta votes on October nineteenth on whether to move toward a referendum on leaving Canada.
Eleven working days is not a lot
The designation falls under the Building Canada Act, a law meant to speed up major projects. Ottawa first planned a one-month consultation on whether to list the pipeline, then stretched it to two months after Indigenous leaders complained about the tight timeline. Chiefs say the real runway was much shorter than that.
Tk'emlúps te Secwépemc Chief Rosanne Casimir told the B.C. Assembly of First Nations meeting that her nation raised process concerns and then waited. "Canada took nearly a month to respond and only eleven working days remained for the review and engagement," she said, as reported by The Canadian Press. She added that communities were asked to wade through thousands of documents with limited funding.
The government admits people were not on board
Major Projects Office head Dawn Farrell faced the room on Wednesday and did not dodge the anger. She said the frustration made her feel like Canada is "never going to work," but promised her office is determined to do better, and she argued the pipeline has already seen deeper consultation than past projects like Trans Mountain.
The government's own summary is blunt. According to a legal analysis from law firm MLT Aikins, Ottawa acknowledged that many communities felt the process was rushed, that they lacked enough information, and that it ran at a time of year when many members were out on the land. Ottawa still concluded that any harm to Indigenous rights could be handled later in the regulatory review.
AP reported that the government said most Indigenous communities it consulted were not prepared to support listing the project. Treaty 8 Grand Chief Trevor Mercredi stood behind Carney and Smith at the announcement, but has said his presence should not be read as support.
Now it is heading to court
On October seventh, Cold Lake First Nation filed for a judicial review in Federal Court. The nation says it was not consulted at all, and it wants the court to quash the designation and declare that Canada owes it a duty to consult. For now it is the only Indigenous community challenging the decision in court, but the same legal analysis notes others could join or file their own cases.
That matters because a designated project is treated as deemed approved, and the rest of the process only decides the conditions for building and running it. Ottawa wants regulatory work done by September of next year so construction can start. A court fight could throw that calendar into doubt.
The money question nobody has answered
The Pacific Link pipeline is also far from a sure thing financially. AP reports a price tag between twenty-five and thirty-one billion dollars, with Ottawa and Alberta putting in roughly two point eight billion before the main private investor, Pembina Pipeline, commits its share. An open season next spring will test whether oil producers will actually sign up to ship on it, and officials admitted the project may not attract enough shippers or financing. If it does go ahead, the pipeline is projected to start operating in twenty thirty-two or twenty thirty-three.
Ottawa has promised Indigenous communities at least a ten percent ownership stake, and Carney has said the "real intensive consultation process will begin now." The government also admitted that the line would enable more oil production and more emissions, which is a tough fit with its climate goals.
What to watch next
A national Indigenous consultation standard is the chiefs' core ask, with protected timelines before decisions are made. At the Vancouver meeting, B.C. chiefs also passed a resolution asking Carney to halt the advance of the Building Canada Act and to repeal Bill C-39 if it clears Parliament. That bill would fast-track approvals, cut review times and create zones of national interest. Chiefs warned that building without free, prior and informed consent risks ending up in court.
The next test comes soon. Chiefs are set to meet Carney and the premiers in Ottawa later this month, and major projects are expected to dominate the agenda. For young Canadians watching the energy, climate and unity debates collide, this is the story to follow: a pipeline pitched as national unity that is already tangled up in the question of who gets a say. More coverage of the fallout is on our Canada page.
Comments 0
No comments yet. Be the first to share your thoughts!
Leave a comment
Share your thoughts. Your email will not be published.